Dry Storage Warehouse

Dry Storage Warehouse 1 / 8
Client
Gay Lea Foods
Duration
5 Weeks
Sector
Food, Industrial
FoodIndustrial

Leona Construction transformed a warehouse space for Gay Lea Foods into a food-grade dry storage facility within 5 weeks. The scope included interior demolition, closing and matching exterior brick at the overhead door, levelling the concrete floor, and applying food-grade paint and epoxy flooring with high bay lighting.

Deliverables

  • Interior demolition
  • Close overhead door and match exterior brick
  • Level concrete floor
  • Food grade paint
  • High bay lights
  • Food-grade Epoxy floor.

This project is part of our General Contracting work.